Our company's ultra-large-diameter engineering drill bits have been perfectly applied in key national projects.

2015-06-11

On June 3, 2015, the Z05 main tower pier of the main bridge over the Guyu Gate waterway for the Fuping Railway’s Pingtan Strait Dual-Use Bridge—a key national project—successfully completed the concrete pouring of a 4.5-meter-diameter bored pile. This pile currently represents one of the largest-diameter foundation piles in the history of bridge construction. The drilling bit used for this borehole was custom-designed and manufactured by Luoyang Jiujiu Technology Co., Ltd., featuring an innovative structural design and robust welding techniques, which provided a solid foundation and ensured high-quality results for the smooth completion of Bored Pile No. 4 at the Z05 pier of the Pingtan Strait Dual-Use Cross-Sea Bridge. Additionally, all eight 4.5-meter-diameter drill bits and 20 4.0-meter-diameter drill bits supplied by our company were seamlessly integrated with the corresponding drilling rigs for this critical project.

  On June 3, 2015, the Z05 main tower pier of the main bridge over the Guyumeng Channel on the Fuping Railway’s Pingtan Strait Dual-Use Bridge—a key national project—completed the concrete pouring for a 4.5-meter-diameter bored pile, which currently represents the largest-diameter pile foundation in the history of bridge construction.

  The drill bit used in this drilling rig is a 4.5-meter-diameter bit designed and manufactured by Luoyang Jiujiu Technology Co., Ltd. Thanks to its innovative design structure and reliable welding technology, it has provided a solid foundation and ensured high-quality results for the successful completion of Drilling Pile No. 4, part of the Z05 bridge pier for the Pingtan Strait Rail-Car Dual-Use Cross-Sea Bridge. Additionally, all eight 4.5-meter-diameter drill bits and 20 4.0-meter-diameter drill bits supplied by our company were seamlessly matched with the corresponding drilling rigs for this project.

NEWS

Earth Pressure TBM Dual-mode Shield and Slurry TBM Dual-mode Shield

Abstract:In long-distance tunnel construction, composite strata with alternating soft soil, fractured surrounding rock and hard rock impose stringent requirements on tunnelling equipment. A single-type shield or TBM often fails to satisfy the requirements of construction safety, ground settlement control and tunnelling efficiency simultaneously. As mainstream composite tunnelling machines, earth pressure TBM dual-mode shields and slurry TBM dual-mode shields are capable of switching between soft-soil balanced tunnelling mode and hard-rock TBM tunnelling mode, making them suitable for tunnel projects with variable geological conditions. This paper introduces the application scope and working principle of the two types of dual-mode shields respectively, and conducts a comparative analysis from dimensions including face stabilization mechanism, mucking method, supporting facilities, construction cost and risk characteristics. It clarifies the selection boundary of the two machines and provides technical references for equipment selection in metro tunnels, water diversion tunnels, river-crossing and sea-crossing tunnels and other projects.

Earth Pressure Balance‑Slurry Dual‑Mode Shield Machine

Abstract: This paper focuses on the earth pressure balance (EPB)‑slurry dual‑mode shield machine, defines its applicable strata and typical engineering scenarios, and elaborates respectively on the working principles and pressure control logic under EPB and slurry tunnelling modes. According to the pressure regulation mechanism of the excavation chamber, the equipment is classified into the direct‑controlled single‑cabin type and the indirect‑controlled air‑cushion double‑cabin type, whose advantages and disadvantages are compared. Finally, from four dimensions including cabin structure, crusher layout, pipeline configuration and grouting logic of the air‑cushion chamber, this paper clarifies the core design differences between the indirect‑controlled dual‑mode shield and the conventional indirect‑controlled air‑cushion slurry shield. The research can provide a technical basis for type selection, structural design and mode‑switching construction of dual‑mode shields for composite‑stratum tunnels. 【This article is compiled for popular science purposes in the industry. Part of the technical data refers to publicly available professional literature.】